CS-197mixed
Multilaser Industrial S.A. (renamed Grupo Multi S.A. in 2023), São Paulo-based maker and distributor of consumer electronics, accessories and toys, listed on B3 since July 2021
Replacement of the 17-year-old Totvs Protheus ERP with SAP S/4HANA (decided 2020, cut-over January 2023), and the stabilisation and cloud migration that followed (2021-2024)
- Region
- Latin America
- Country
- Brazil
- Industry
- Consumer Electronics and Devices (Discrete Manufacturing)
- Functions
- IT, ERP & Digital, Operations & Service Delivery, Supply Chain & Logistics, Finance & FP&A, Manufacturing & Production
- Topics
- Legacy ERP and fragmented systems block execution; Operations cannot meet demand efficiently; Margins are eroding despite revenue; Cash is trapped and liquidity is tightening; Inventory is simultaneously excessive and unavailable
- Starting situation
- New initiative
- Period
- 2021–2024
- Last verified
- 5 November 2026
Executive summary
Multilaser, a Brazilian maker and distributor of electronics, accessories and toys with net revenue of R$4.8bn in 2021, decided at the end of 2020 to replace the ERP it had used and customised for 17 years with SAP S/4HANA [C01, C06]. The plan was a phased rollout, a first phase of about nine months, and a promise of some pain but no impact on operations [C02, C03].
The core cut-over came in January 2023, about a year after the first phase was due, in the middle of a demand slump and an inventory clearance [C10, C13]. It froze the business: revenue ran at about 30% of normal in January, invoices had to be reissued by hand, and the company booked the first gross loss in its history; the chief executive said most of that quarter's loss was tied directly to the migration [C14, C15, C16].
The system was kept and stabilised. By March 2023 billing had reached its target; in 2024 the ERP moved to the cloud without disruption; and in March 2025 the chief executive called it quite stable and much better than the old one [C15, C22, C24]. The lesson for a mid-sized manufacturer and distributor: an ERP cut-over is an operational event, not an IT one, and its timing and fallback must be decided against the state of the business on the day.
Outcome: mixed
Documented shortfalls or reversals sit alongside documented gains. For example: an initial failure later recovered, or a strategic goal met while a major adverse event in the same programme was recorded.
Basis of the outcome
The stated aim was to replace a heavily customised ERP with SAP S/4HANA in phases, with the first phase taking about nine months, and, in the IT director's words, to expect some pain but nothing that would affect operations (S01). The documented shortfall: the core cut-over came in January 2023, about a year after the first phase was due, and froze the business. Revenue ran at about 30% of normal in January and 50% in February, wrong invoices had to be reissued by hand, and the company recorded the first gross loss in its history in the first quarter of 2023, most of which the chief executive said was tied directly to the migration's costs and problems (S06). The documented gains: management described March 2023 as a month of stabilisation (S05, S07); in 2024 the ERP's cloud infrastructure was migrated without disruption (S13); and in March 2025 the chief executive described the ERP as quite stable and much better than the old system, with some modules still to come (S14). The system was not abandoned or written down. An initial failure later recovered fits the mixed class. The company remained loss-making in 2023 and 2024 for reasons that also include weak demand, high-cost inventory and exchange rates (S03, S14).
Key figures
| Phase | Figure | Value | When | Verification |
|---|---|---|---|---|
| Before | Net revenue | R$4,846.7m | 2021 | audited_filing |
| Before | Planned first phase | about 9 months | Apr 2021 | press_reported |
| During | Fourth-quarter G&A rise on prior quarter | +122.8% | 4Q 2022 | company_reported |
| During | Revenue versus normal | about 30% | Jan 2023 | company_reported |
| During | Net loss | R$342.6m | 1Q 2023 | company_reported |
| During | Distribution expenses | +46.4% year on year | 1Q 2023 | company_reported |
| After | Net loss | R$836.2m | 2023 | company_reported |
| After | EBITDA | R$41.4m | 2024 | company_reported |
- audited_filing
- A figure in audited financial statements, such as an annual report's financial statements or a 10-K.
- press_reported
- A journalist's own reporting.
- company_reported
- A company statement, press release or investor presentation that no one has independently checked.
Practices this case bears on
- SupportsGate every go-live on measured readiness, not on the calendar BP-001
- SupportsDecide what truly differentiates before buying standard software; change the process for everything else BP-002
- SupportsMake a few quantified, dated commitments, publish them, and report against them, including the misses BP-004
- SupportsRoll out operational and system change in waves, each proven before the next BP-006
- SupportsTie every benefit to the financial statements, bank it before counting it, and keep tracking after the programme ends BP-010
- SupportsSimplify what you sell and the rules you run before you automate or scale them BP-011
- SupportsLimit how many things change at once, for the business and for the customer BP-012
- SupportsSequence customer-facing cutovers last, rehearse failure at full scale, and make resilience a programme outcome BP-014
- SupportsDefine and freeze each programme metric before reporting it, and keep it comparable BP-034
- SupportsFinance and size big bets so the company survives a downturn in the first years BP-040
- SupportsRe-plan openly when the facts change, rather than defending the old timetable BP-043
- SupportsSecure the cash runway before you need it, and measure liquidity at its worst point BP-044
- SupportsRecognise restructuring and integration costs early, in full, and separately from the savings BP-047
- SupportsWhen a failure hits customers, tell them early, fix it completely, and compensate consistently BP-066
Sources
- S01 Multilaser troca Protheus por S/4 Hana · Luana Rosales, Baguete, 2021-04-09 · accessed 2026-11-05
- S02 Sobrou para a SAP na Multilaser · Maurício Renner, Baguete, 2023-03-30 · accessed 2026-11-05
- S03 Multilaser derrete 35% com o pior resultado de sua história · Pedro Arbex, Brazil Journal, 2023-03-29 · accessed 2026-11-05
- S04 O que está por trás da 'pane' das ações da Multi (ex-Multilaser) na B3? · Liliane de Lima, Seu Dinheiro, 2023-03-29 · accessed 2026-11-05
- S05 Multilaser Industrial S.A.: Demonstrações contábeis individuais e consolidadas em 31 de dezembro de 2022, com relatório da administração · Multilaser Industrial S.A., Multilaser Industrial S.A. (investor relations document service), 2023-03-28 · accessed 2026-11-05
- S06 Multilaser Industrial S.A.: Release de resultados 1T23 · Multilaser Industrial S.A., Multilaser Industrial S.A. (investor relations document service), 2023-05-15 · accessed 2026-11-05
- S07 Ação do Grupo Multi desaba após prejuízo no 4º tri e prognóstico negativo para 1º tri · Reuters, Money Times, 2023-03-29 · accessed 2026-11-05
- S08 Ex-Multilaser (MLAS3) desaba quase 37%; 4º tri foi 'tempestade perfeita' e demonstra dificuldade do setor no Brasil, diz BBA · Lara Rizério, InfoMoney, 2023-03-29 · accessed 2026-11-05
- S09 'Caaaaaixa à vista': as aventuras do CEO do Grupo Multi em mares revoltos · Karina Souza, Exame, 2023-11-15 · accessed 2026-11-05
- S10 Multi: Quem esperar melhora no curtíssimo prazo vai se decepcionar, diz CEO · not stated, Brazil Journal, 2023-12-13 · accessed 2026-11-05
- S11 Grupo Multi S.A.: Release de resultados 1T24 · Grupo Multi S.A., Grupo Multi S.A. (investor relations document service), 2024-05-14 · accessed 2026-11-05
- S12 Multi (ex-Multilaser) enxuga portfólio para melhorar margens e voltar a dar lucro · Felipe Mendes, InfoMoney, 2024-05-16 · accessed 2026-11-05
- S13 Grupo Multi S.A.: Release de resultados 2T24 · Grupo Multi S.A., Grupo Multi S.A. (investor relations document service), 2024-08-13 · accessed 2026-11-05
- S14 Grupo Multi S.A.: Resultados do 4T24 e 2024 · Grupo Multi S.A., Grupo Multi S.A. (investor relations document service), 2025-03-26 · accessed 2026-11-05
- S15 Após IPO, Multilaser quer ampliar portfólio de produtos e crescer fora do Brasil · Matheus Prado, CNN Brasil, 2021-09-14 · accessed 2026-11-05
- S16 Fras-le: ERP freia lucro · Maurício Renner, Baguete, 2012-05-09 · accessed 2026-11-05
Researched and fact-checked knowledgebase · Knowledgebase built 5 November 2026 · Last verified 5 November 2026
Practices, their evidence grades and case summaries are public. Full case studies are available in AXIOM to subscribers and AXIOM Discover participants.