CS-037failure
UK Department of Health / NHS in England
National Programme for IT in the NHS (NPfIT), 2002–2011
- Region
- Western Europe
- Country
- United Kingdom
- Industry
- Hospitals and Health Systems
- Functions
- IT, ERP & Digital, Strategy, Corporate Development & Transformation Office, Procurement & Strategic Sourcing, Operations & Service Delivery, Data, Analytics & AI
- Topics
- Legacy ERP and fragmented systems block execution; Technology spending is growing without business returns; Competing transformation programs overwhelm resources; Cross-functional processes are slow and broken; Data cannot be trusted for critical decisions
- Starting situation
- New initiative
- Period
- 2002–2011
- Last verified
- 1 November 2026
Executive summary
In June 2002 the UK government launched the National Programme for IT in the NHS, a ten-year effort to give the NHS in England a national care records service, digital imaging, electronic prescribing, electronic booking and a national network and data spine [C05]. Its contracts were let centrally, fast, and on fixed prices to four large Local Service Providers, with suppliers paid only once systems worked [C06, C07, C08].
Much of the national infrastructure arrived, but the core detailed care records systems did not [C12, C37]. By March 2011, systems had reached 19 of 122 contracted acute trusts, after the contracted number had already been cut [C33]. In September 2011 the government announced an accelerated dismantling after a Major Projects Authority review concluded the programme could not deliver to its original intent [C37].
The three numbers that matter: £2.7bn spent on care records systems that the NAO said did not represent value for money [C31]; a total cost estimate that moved from £12.4bn (2006) to £12.7bn (2008), £11.4bn (2011) and £9.8bn (2013), on different bases [C06, C24, C32, C39]; and a full-deployment date that moved from 2010 to 2014-15 before the NAO found in 2011 that the vision had been compromised [C11, C25, C35].
The one lesson (KB inference): central procurement can buy scale and price, but it cannot buy adoption; when the users who must change their work are engaged after the contracts are signed, the contracts lock in a design the users may not accept [C10, C16, C41].
Outcome: failure
The initiative was abandoned, exited or written down, or an official finding called it a failure.
Basis of the outcome
The National Audit Office concluded in 2011 that the £2.7bn spent on care records systems did not represent value for money, and that the programme would not deliver an electronic record for every NHS patient. In September 2011 the government announced an accelerated dismantling of the programme after a Major Projects Authority review found it could not deliver to its original intent. Several national components (the Spine, N3, NHSmail, Choose and Book, PACS) continued, so the failure finding applies to the programme as designed and above all to its core detailed care records element.
Key figures
| Phase | Figure | Value | When | Verification |
|---|---|---|---|---|
| Before | Gross projected spend (not a budget) | £12.4bn over ten years at 2004-05 prices | 2006 | official_finding |
| During | Spend vs expected to March 2006 | £654m vs £1,448m | 2006 | official_finding |
| During | Total cost estimate | £12.7bn | May 2008 | official_finding |
| During | Care records full deployment (revised) | 2014-15, some four years late | May 2008 | official_finding |
| During | Fujitsu South contract terminated | £896m contract; £151m paid | 2008 | official_finding |
| After | Care records spend judged not value for money | £2.7bn | May 2011 | official_finding |
| After | Acute trusts with detailed care records systems | 19 of 122 contracted (from 171 originally) | Mar 2011 | official_finding |
| After | Total spent at dismantling announcement | £6.4bn | Sep 2011 | official_statement |
| After | Lifetime cost forecast vs benefits to Mar 2012 | £9.8bn cost; £3.7bn benefits to date | Jun 2013 | official_finding |
| After | CSC/Lorenzo scope | From 220 trusts (£3.1bn) to 22 trusts (about £2.2bn contract) | Sep 2013 | official_finding |
- official_finding
- A finding of an inquiry, court or regulator.
- official_statement
- A government or ministerial statement. It is official, but political, and is not a finding.
Practices this case bears on
- MixedDecide what truly differentiates before buying standard software; change the process for everything else BP-002
- SupportsName one accountable sponsor, keep sponsorship stable, and treat a leadership change as a re-baselining event BP-003
- SupportsWhen the thesis has failed, exit in one decisive move and say what is kept BP-007
- SupportsMake line managers and the front line own the change, and train users before they get access BP-009
- SupportsTie every benefit to the financial statements, bank it before counting it, and keep tracking after the programme ends BP-010
- SupportsOutsource only what does not differentiate, and keep the capability to specify, integrate and replace partners BP-017
- SupportsProtect the integrity of procurement and appointments, and test feasibility before signing long contracts BP-068
Sources
- S01 Department of Health: The National Programme for IT in the NHS (HC 1173, Session 2005-06), executive summary · Comptroller and Auditor General, National Audit Office, 2006-06 · accessed 2026-11-01
- S02 The National Programme for IT in the NHS: Progress since 2006 (HC 484-I, Session 2007-08), executive summary · Comptroller and Auditor General, National Audit Office, 2008-05-16 · accessed 2026-11-01
- S03 The National Programme for IT in the NHS: an update on the delivery of detailed care records systems (HC 888, Session 2010-12), executive summary · Comptroller and Auditor General, National Audit Office, 2011-05 · accessed 2026-11-01
- S04 Department of Health: The National Programme for IT in the NHS, Twentieth Report of Session 2006-07 (HC 390), summary · Committee of Public Accounts, House of Commons Committee of Public Accounts, 2007-04 · accessed 2026-11-01
- S05 Department of Health: The National Programme for IT in the NHS, Twentieth Report of Session 2006-07 (HC 390), introduction paras 1-6 · Committee of Public Accounts, House of Commons Committee of Public Accounts, 2007-04-11 · accessed 2026-11-01
- S06 PAC report brings brickbats and bouquets for NPfIT · E-Health Insider, E-Health Insider (now Digital Health), 2007-04-18 · accessed 2026-11-01
- S07 Accenture pulls out of national programme · E-Health Insider, E-Health Insider (now Digital Health), 2006-09-28 · accessed 2026-11-01
- S08 The National Programme for IT in the NHS: A Case History · Oliver Campion-Awwad, Alexander Hayton, Leila Smith, Mark Vuaran, University of Cambridge, MPhil in Public Policy (hosted by the Computer Laboratory), 2014-02 · accessed 2026-11-01
- S09 Committee of Public Accounts news: report on the National Programme for IT in the NHS (45th Report, Session 2010-12) · Committee of Public Accounts, UK Parliament, 2011-08-03 · accessed 2026-11-01
- S10 Dismantling the NHS National Programme for IT · Department of Health, Department of Health / GOV.UK, 2011-09-22 · accessed 2026-11-01
- S11 Review of the final benefits statement for programmes previously managed under the National Programme for IT in the NHS (memorandum for the Committee of Public Accounts) · National Audit Office, National Audit Office, 2013-06 · accessed 2026-11-01
- S12 Committee of Public Accounts news: The dismantled National Programme for IT in the NHS · Committee of Public Accounts, UK Parliament, 2013-09-18 · accessed 2026-11-01
- S13 DH loses Fujitsu dispute · E-Health Insider, E-Health Insider (now Digital Health), 2014-07-28 · accessed 2026-11-01
- S14 Department of Health: The National Programme for IT in the NHS, Twentieth Report of Session 2006-07 (HC 390): Conclusions and recommendations · Committee of Public Accounts, House of Commons Committee of Public Accounts, 2007-04-11 · accessed 2026-11-01