CS-037failure

UK Department of Health / NHS in England

National Programme for IT in the NHS (NPfIT), 2002–2011

Region
Western Europe
Country
United Kingdom
Industry
Hospitals and Health Systems
Functions
IT, ERP & Digital, Strategy, Corporate Development & Transformation Office, Procurement & Strategic Sourcing, Operations & Service Delivery, Data, Analytics & AI
Topics
Legacy ERP and fragmented systems block execution; Technology spending is growing without business returns; Competing transformation programs overwhelm resources; Cross-functional processes are slow and broken; Data cannot be trusted for critical decisions
Starting situation
New initiative
Period
2002–2011
Last verified
1 November 2026

Executive summary

In June 2002 the UK government launched the National Programme for IT in the NHS, a ten-year effort to give the NHS in England a national care records service, digital imaging, electronic prescribing, electronic booking and a national network and data spine [C05]. Its contracts were let centrally, fast, and on fixed prices to four large Local Service Providers, with suppliers paid only once systems worked [C06, C07, C08].

Much of the national infrastructure arrived, but the core detailed care records systems did not [C12, C37]. By March 2011, systems had reached 19 of 122 contracted acute trusts, after the contracted number had already been cut [C33]. In September 2011 the government announced an accelerated dismantling after a Major Projects Authority review concluded the programme could not deliver to its original intent [C37].

The three numbers that matter: £2.7bn spent on care records systems that the NAO said did not represent value for money [C31]; a total cost estimate that moved from £12.4bn (2006) to £12.7bn (2008), £11.4bn (2011) and £9.8bn (2013), on different bases [C06, C24, C32, C39]; and a full-deployment date that moved from 2010 to 2014-15 before the NAO found in 2011 that the vision had been compromised [C11, C25, C35].

The one lesson (KB inference): central procurement can buy scale and price, but it cannot buy adoption; when the users who must change their work are engaged after the contracts are signed, the contracts lock in a design the users may not accept [C10, C16, C41].

Outcome: failure

The initiative was abandoned, exited or written down, or an official finding called it a failure.

Basis of the outcome

The National Audit Office concluded in 2011 that the £2.7bn spent on care records systems did not represent value for money, and that the programme would not deliver an electronic record for every NHS patient. In September 2011 the government announced an accelerated dismantling of the programme after a Major Projects Authority review found it could not deliver to its original intent. Several national components (the Spine, N3, NHSmail, Choose and Book, PACS) continued, so the failure finding applies to the programme as designed and above all to its core detailed care records element.

Key figures

PhaseFigureValueWhenVerification
BeforeGross projected spend (not a budget)£12.4bn over ten years at 2004-05 prices2006official_finding
DuringSpend vs expected to March 2006£654m vs £1,448m2006official_finding
DuringTotal cost estimate£12.7bnMay 2008official_finding
DuringCare records full deployment (revised)2014-15, some four years lateMay 2008official_finding
DuringFujitsu South contract terminated£896m contract; £151m paid2008official_finding
AfterCare records spend judged not value for money£2.7bnMay 2011official_finding
AfterAcute trusts with detailed care records systems19 of 122 contracted (from 171 originally)Mar 2011official_finding
AfterTotal spent at dismantling announcement£6.4bnSep 2011official_statement
AfterLifetime cost forecast vs benefits to Mar 2012£9.8bn cost; £3.7bn benefits to dateJun 2013official_finding
AfterCSC/Lorenzo scopeFrom 220 trusts (£3.1bn) to 22 trusts (about £2.2bn contract)Sep 2013official_finding
official_finding
A finding of an inquiry, court or regulator.
official_statement
A government or ministerial statement. It is official, but political, and is not a finding.

Sources

  1. S01 Department of Health: The National Programme for IT in the NHS (HC 1173, Session 2005-06), executive summary · Comptroller and Auditor General, National Audit Office, 2006-06 · accessed 2026-11-01
  2. S02 The National Programme for IT in the NHS: Progress since 2006 (HC 484-I, Session 2007-08), executive summary · Comptroller and Auditor General, National Audit Office, 2008-05-16 · accessed 2026-11-01
  3. S03 The National Programme for IT in the NHS: an update on the delivery of detailed care records systems (HC 888, Session 2010-12), executive summary · Comptroller and Auditor General, National Audit Office, 2011-05 · accessed 2026-11-01
  4. S04 Department of Health: The National Programme for IT in the NHS, Twentieth Report of Session 2006-07 (HC 390), summary · Committee of Public Accounts, House of Commons Committee of Public Accounts, 2007-04 · accessed 2026-11-01
  5. S05 Department of Health: The National Programme for IT in the NHS, Twentieth Report of Session 2006-07 (HC 390), introduction paras 1-6 · Committee of Public Accounts, House of Commons Committee of Public Accounts, 2007-04-11 · accessed 2026-11-01
  6. S06 PAC report brings brickbats and bouquets for NPfIT · E-Health Insider, E-Health Insider (now Digital Health), 2007-04-18 · accessed 2026-11-01
  7. S07 Accenture pulls out of national programme · E-Health Insider, E-Health Insider (now Digital Health), 2006-09-28 · accessed 2026-11-01
  8. S08 The National Programme for IT in the NHS: A Case History · Oliver Campion-Awwad, Alexander Hayton, Leila Smith, Mark Vuaran, University of Cambridge, MPhil in Public Policy (hosted by the Computer Laboratory), 2014-02 · accessed 2026-11-01
  9. S09 Committee of Public Accounts news: report on the National Programme for IT in the NHS (45th Report, Session 2010-12) · Committee of Public Accounts, UK Parliament, 2011-08-03 · accessed 2026-11-01
  10. S10 Dismantling the NHS National Programme for IT · Department of Health, Department of Health / GOV.UK, 2011-09-22 · accessed 2026-11-01
  11. S11 Review of the final benefits statement for programmes previously managed under the National Programme for IT in the NHS (memorandum for the Committee of Public Accounts) · National Audit Office, National Audit Office, 2013-06 · accessed 2026-11-01
  12. S12 Committee of Public Accounts news: The dismantled National Programme for IT in the NHS · Committee of Public Accounts, UK Parliament, 2013-09-18 · accessed 2026-11-01
  13. S13 DH loses Fujitsu dispute · E-Health Insider, E-Health Insider (now Digital Health), 2014-07-28 · accessed 2026-11-01
  14. S14 Department of Health: The National Programme for IT in the NHS, Twentieth Report of Session 2006-07 (HC 390): Conclusions and recommendations · Committee of Public Accounts, House of Commons Committee of Public Accounts, 2007-04-11 · accessed 2026-11-01