CS-194failure
Better Place (Better Place Inc. and its Israeli and Danish operating companies), controlled by Israel Corporation
Battery-swap electric-car network in Israel and Denmark with the Renault Fluence Z.E. (2007-2013), ending in liquidation
- Region
- Middle East, Western Europe
- Country
- Israel, Denmark, United States, Australia
- Industry
- Renewable Fuels, Fueling Infrastructure and Credits
- Functions
- Product, R&D & Innovation, Marketing & Go-to-Market, Operations & Service Delivery, Strategy, Corporate Development & Transformation Office, Treasury & Working Capital
- Topics
- Investment capital is not generating returns; The business model is being disrupted; Cash is trapped and liquidity is tightening; Innovation is too slow to defend competitiveness
- Starting situation
- New initiative
- Period
- 2007–2013
- Last verified
- 5 November 2026
Executive summary
Better Place set out in 2007 to make electric cars as convenient as petrol cars by owning the batteries and the network: drivers would buy the car, lease the battery, charge at home and swap batteries at stations on long trips [C01, C11]. In 2009 it agreed with Renault to sell at least 100,000 cars in Israel and Denmark by 2016 [C01].
Sales began only in 2012, and by May 2013 somewhere between fewer than 1,000 and barely 2,000 cars had been sold, depending on the account [C08, C09, C14]. The company lost US$454m in 2012 on US$7m of revenue, its cash fell from US$293m to US$34m, and its controlling shareholder declined to invest more [C05, C08].
It applied for liquidation in May 2013, and the Israeli business was sold for about US$5m after losses of more than NIS 3bn [C08, C15]. The lesson: an infrastructure model that needs carmakers, customers and capital to arrive together must prove one market at small scale before it builds for many.
Outcome: failure
The initiative was abandoned, exited or written down, or an official finding called it a failure.
Basis of the outcome
The aim, set with Renault in 2009, was a battery-swap and charging network in Israel and Denmark with at least 100,000 electric cars sold by 2016 (S01). By mid-2013 between about 950 (Israel only) and barely 2,000 cars had been sold, depending on the source, the 2012 loss was US$454m on about US$7m of revenue, and the auditor had attached a going-concern warning (S05, S08, S11, S15). The controlling shareholder declined to invest further, the company filed for bankruptcy in May 2013 and its four Israeli companies filed for liquidation in early June, and in July 2013 the court approved the sale of the Israeli operations for NIS 18m (about US$5m) after losses of more than NIS 3bn (S08, S15, S16). The controlling shareholder had already written its investment down from US$101m to US$16m (S05). The initiative was abandoned through liquidation and written down, which meets the failure criterion.
Key figures
| Phase | Figure | Value | When | Verification |
|---|---|---|---|---|
| Before | Volume commitment with Renault | at least 100,000 cars by 2016 | 2009 | press_reported |
| Before | Capital raised | about US$850m | 2007-2013 | press_reported |
| During | Losses to end-2011 | US$360m, with no revenue | 2011 | press_reported |
| During | Net loss | US$454m on revenue of US$7m | 2012 | press_reported |
| During | Swap stations in Israel | 38 | 2013 | press_reported |
| After | Cars sold in Israel | about 950 | 2013 | press_reported |
| After | Sale price of Israeli business | NIS 18m | 2013 | press_reported |
| After | Renault's secured claim | €65m | 2013 | press_reported |
- press_reported
- A journalist's own reporting.
Practices this case bears on
- SupportsRoll out operational and system change in waves, each proven before the next BP-006
- SupportsWhen the thesis has failed, exit in one decisive move and say what is kept BP-007
- SupportsTreat vendor attestations, awards and executive testimony as claims to test, not as assurance BP-019
- SupportsBuild independent challenge into the board for transformational bets BP-024
- SupportsAnnounce only targets the evidence supports, build synergy estimates from shared data, and re-base them openly BP-033
- SupportsDefine and freeze each programme metric before reporting it, and keep it comparable BP-034
- SupportsJudge growth and customer strategies by unit economics and customer behaviour, not by totals or activity BP-037
- SupportsSet a walk-away price from stand-alone value plus provable synergies, and re-test the deal when it changes BP-039
- SupportsFinance and size big bets so the company survives a downturn in the first years BP-040
- SupportsWrite exit and pause criteria at approval, and treat impairments as triggers to re-test the strategy BP-042
- SupportsSecure the cash runway before you need it, and measure liquidity at its worst point BP-044
- SupportsFix the core product and operation before amplifying the channel or scaling the new strategy BP-045
- SupportsValidate the proposition with the target customers' own evidence and a control-market pilot before a national launch BP-057
- SupportsDesign the offer around what the profitable customer values, strip what they do not, and build the cost structure for the price BP-058
- SupportsMake the economics work for every node of the ecosystem, and re-price shared contracts before you outgrow them BP-060
- SupportsMap critical dependencies several tiers deep, buffer what cannot be re-sourced, and decide who pays for resilience BP-064
- SupportsWhen a failure hits customers, tell them early, fix it completely, and compensate consistently BP-066
- SupportsDiagnose the root cause and the gap to the best before choosing the remedy BP-069
- SupportsUse partnerships to buy speed or share risk, but price in their execution risk and plan for some to fail BP-070
Sources
- S01 Renault, Better Place to Sell 100,000 Electric Vehicles by 2016 · Agence France-Presse, IndustryWeek (Agence France-Presse), 2009-09-16 · accessed 2026-11-05
- S02 Better Place Australia CEO Evan Thornley Named Global Chief Executive Officer · Better Place, Business Wire (republished by Business Wire China), 2012-10-08 · accessed 2026-11-05
- S03 After surprise ouster, Better Place hopes new CEO will recharge electric car firm's fortunes · David Shamah, The Times of Israel, 2012-10-03 · accessed 2026-11-05
- S04 Better Place losses reach $360m · Tamar Koblenz, Globes, 2012-03-29 · accessed 2026-11-05
- S05 Better Place receives "going concern" warning · Aviv Levy, Globes, 2013-03-21 · accessed 2026-11-05
- S06 Better Place needs to raise $500m · Efrat Peretz, Globes, 2013-04-04 · accessed 2026-11-05
- S07 How electric-car startup Better Place went to a worse one and lost $815 million along the way · not stated, Quartz, 2013-05 · accessed 2026-11-05
- S08 Better Place files for bankruptcy · Gavriel Fiske, The Times of Israel, 2013-05-26 · accessed 2026-11-05
- S09 Trailblazing Israeli electric car company to close (Update 2) · Associated Press, Associated Press (via Phys.org), 2013-05-26 · accessed 2026-11-05
- S10 No Better Place: How the battery swap idea lost its charge · Giles Parkinson, RenewEconomy, 2013-05-26 · accessed 2026-11-05
- S11 Battery-switching car pioneer Better Place files for bankruptcy · John Voelcker, The Christian Science Monitor, 2013-05-26 · accessed 2026-11-05
- S12 Renault blindsided by Better Place liquidation · Ela Levy-Weinrib, Globes, 2013-05-27 · accessed 2026-11-05
- S13 The car's out of juice, but the Better Place vision may drive on · David Shamah, The Times of Israel, 2013-05-28 · accessed 2026-11-05
- S14 What caused Israel's promising electric car maker to fail · Ben Sales, J. The Jewish News of Northern California (JTA), 2013-06-07 · accessed 2026-11-05
- S15 Better Place sold for NIS 43M after losing 3B · Shahar Haselkorn, Ynetnews, 2013-07-10 · accessed 2026-11-05
- S16 Better Place buyers fail to meet payments · Ela Levy-Weinrib, Globes, 2013-07-31 · accessed 2026-11-05
- S17 New Better Place Post-Mortem Pins All Blame on Agassi's Megalomania · Assaf Oron, InsideEVs, 2014-04-15 · accessed 2026-11-05
- S18 A detailed look at the dreams and failure of Better Place · Sebastian Blanco, Autoblog, 2014-04-18 · accessed 2026-11-05
Researched and fact-checked knowledgebase · Knowledgebase built 5 November 2026 · Last verified 5 November 2026
Practices, their evidence grades and case summaries are public. Full case studies are available in AXIOM to subscribers and AXIOM Discover participants.