BP-013Grade B29 supporting cases (28 counted), 0 counter-examples
Budget the whole-life cost of a core programme, treat budget rises as new decisions, and retire legacy on a dated plan
The practice
Budget for build, stabilisation, run cost, amortisation and the cost of failure; treat any scope-driven budget rise as a new decision with a revised benefits case; and retire legacy platforms on a funded, dated plan.
Why it works
The visible budget of a core-system or store-estate programme is usually the build. Stabilisation, the amortisation tail, the run cost of two platforms in parallel and the cost of a failed go-live are often larger, and they arrive after approval when the decision can no longer be revisited cheaply. When budget and scope collide, cutting the functions that make the system usable saves money on paper and moves cost into operations. Treating a budget rise as a new decision forces the benefits case to be re-tested rather than assumed. Legacy platforms kept alive 'temporarily' become permanent cost and risk unless their retirement is dated and funded. Flyvbjerg and Budzier's data show IT overruns have a fat tail [R4], which supports budgeting for the tail rather than the mean.
KB synthesis: the mechanism is the knowledgebase's own reasoning, drawn from the member lessons. Factual support is the case claims under evidence.cases and the research under evidence.research (R-refs).
How to apply it
- Present a whole-life cost: build, stabilisation, parallel run, amortisation, run cost and a contingency sized to the overrun tail.
- Set a threshold (for example 10% of budget) above which a rise returns to the board with a revised benefits case.
- When budget and scope collide, escalate; do not cut usability-critical functions silently.
- Record integration shortcuts as technical debt with a repayment date.
- Fund and date the decommissioning of each legacy platform in the business case.
Warning signs
- Contingency is a round percentage unrelated to the risk profile.
- Two platforms are planned to run in parallel 'for a transition period' with no end date.
- Run-cost estimates are missing from the business case.
- Scope cuts are reported as savings.
When it applies
- Core-system replacements, store-estate and network programmes, and post-merger platform consolidation.
When it does not
- Small, modular changes whose run cost is trivial and whose failure is reversible.
Evidence grade: Grade B
At least 6 counted supporting cases for every 100 cases in the knowledgebase (6 × cases ÷ 100, rounded to the nearest whole number), whose primary regions span at least 4 regions.
Why this grade
Grade B by schema 4.10 route: >=14 counted cases across >=4 primary regions (the case bar is 6 per 100 cases in the knowledgebase, 235 cases). A needs a systematic, peer-reviewed study that tests this practice. None of the research cited in the KB does (R4 supports the mechanism only, not the practice). 1 supporting case(s) rest only on company-reported claims and are not counted toward the grade.
Where it applies
- Transformation type
- Topic (business problem)
- Function
- Starting situation
- Industry
- Region
Supporting and counter cases
Queensland Health (State of Queensland), with IBM as prime contractor CS-003
Standard Bank Group CS-061
Nike, Inc. CS-005
Marks and Spencer Group plc CS-055
Government of Canada (Public Services and Procurement Canada) CS-038
Nokia Corporation CS-066
Sprint Nextel Corporation CS-083
County of Marin, California CS-105
Bancolombia S.A. (Grupo Bancolombia, renamed Grupo Cibest) and its digital platform Nequi CS-129
Mizuho Financial Group, Inc. and its banking subsidiary Mizuho Bank, Ltd. (Japan) CS-156
Kenya Revenue Authority (KRA), the national tax administration of Kenya CS-159
Research
Among 1,471 IT projects, about one in six had an average cost overrun of 200%, against a 27% average.
Dataset of 1,471 IT projects with a stated method (academic preprint). It measures cost and schedule overruns, not the effect of any practice.
Why Your IT Project Might Be Riskier Than You Think · Flyvbjerg and Budzier, arXiv, 2013
Researched and fact-checked knowledgebase · Knowledgebase built 5 November 2026